NCAA Certification

Tentative Certification Timeline |
|
| Printable Version | |
Date |
Item |
| August 26, 2010 | Dates of steering/subcommittee meetings: |
| September - October 2010 | Data Gathering |
| October - December 2010 | Responding to self-study items: Sub Committees draft responses. |
| February - March 2011 | Campus and community review of the draft documents. |
| December 2010 - March 2011 | Review of the draft documents by the Steering committee (and others). |
| April 2011 | Plans for improvement will be finalized. |
| March - April 2011 | Preparing final report. |
| April 2011 | Reviewing final ACS report. |
| April 29, 2011 | Submitting final ACS report to NCAA. |
| August 2011 | Responding to committee-identified issues. |
| September 12 - November 18 | Conducting peer-review team visit. (Three day on-site visit.) |
| November - December 2011 | Responding to peer-review team's report. |
| Fall 2010 - February 2012 | Communicating work of the Steering Committee to institutional community, electronic and print media. |