ESG Impact Change Impact icon symbol 

Project timeline image

Click image to view larger version of the project timeline.

Work Completed

✓ LOA portion of ATS identified as Phase 1

✓ Project Plan for LOA

✓ Hours for LOA separated from other deliverables on ATS (172 hrs LOA & 142 hrs remaining) 

Next Steps

  • Confirm data elements to be transferred
  • Initiate purchase of integration pieces
  • Secure Ellucian professional services

Risks Identified

  • Professional contracts and integration purchased could delay timeline
  • Schedule depends on HR's bandwidth to complete training with all departments